Standard Form of Building Contracts Compared

RM495.00RM620.00

Author: Datuk Professor Sundra Rajoo
Publication Date: Dec, 2021
ISBN: 9789672701187
Country:
 Malaysia
Format: Paperback, 2 volumes

It is the first book of its kind comparing selected domestic and international standard form of building contracts. It is a complete compendium on construction law as practised in standard form of building contracts as follows:

Division 1: Historical Development of the selected Standard Form of Building Contracts This Division provides a general introduction based on the historical development, overview and comment on its practicality and popularity, etc of the selected standard form of building contracts. There is a discussion on the judicial interpretation and development pertaining to these standard form of building contracts.

Division 2: Selected Standard Form of Building Contracts are compared including PAM Form 2018, AIAC (2019), PWD 203A, CIDB (2000), IEM (2017), FIDIC Red Book (2017) and JCT (2016) This Division provides a comparative overview on the differences and similarities of the selected standard form of contracts. The PAM Form 2018 is used as the starting point and six (6) different standard form of building contracts are selected for comparison namely, AIAC (2019), PWD 203A, CIDB (2000), IEM (2017), FIDIC Red Book (2017) and JCT (2016).

Division 3: PAM Form 2018 compared with other selected Standard Form of Building Contracts This Division provides a detailed commentary of the PAM Form 2018 with comparison of relevant clauses of selected standard form of building contracts. It includes analysis, comments, observations and applicable legal authorities on PAM Form 2018 together with discussion on the differences and similarities among the other selected standard form of building contracts.

Division 4: Other clauses provided in other selected Standard Form of Building Contracts, not in the PAM Form 2018 This Division provides a detailed discussion of the key subject matters of the selected standard form of building contracts which are not found in the PAM Form 2018.

This book is written with the support of special contributors, Ir. Harbans Singh K. S. and Lam Wai Loon together with a group of talented young lawyers as part of the Editorial Board consisting of Ng Chu Yin (also qualified as a Quantity Surveyor), Heather Yee Jing Wah, Lee Kai Jun, Naveen Sri Kantha, Leong Chee Weng, Sameera Hassan, James Ding Tse Wen, Ashley Ooi Hui Ying and Ankit Sanghvi.


Chapters Contents
– Foreword 1
– Foreword 2
– Foreword 3
– Preface and Acknowledgements
– The Author
– Special Contributors
– Editorial Board
– Table of Cases
– Table of Statutes
– Table of Subsidiary Legislation
– Table of Foreign Legislation
Volume 1 – Division 1: Historical Development of the Standard Form of Building Contracts
1.1 Overview
1.2 Malaysian Government/Public Sector Enterprises Contracts
1.3 Private Sector Contracts
1.4 International Standard Form of Contracts
1.5 The Scope of the Book
Division 2: The PAM Form 2018, the AIAC (2019), the PWD 203A, the CIDB (2000), the IEM (2017), the JCT (2016) and the FIDIC Red Book (2017) are the Selected Standard Form of Building Contracts Compared
1 Overview
2 Contractor’s General Obligations
2.1 Commentary on Contractor’s General Obligations
3 Materials, Goods and Workmanship to Conform to Description, Testing and Inspection
3.1 Comparison of Materials, Goods and Workmanship to Conform to Description, Testing and Inspection Clause Between PAM Form 2018 and the Other Standard Form of Contracts
4 Variation, Provisional and Prime Cost Sums
4.1 Comparison of Variation, Provisional and Prime Cost Sums Clause Between PAM Form 2018 and the Selected Standard Form of Contracts
4.2 Definition of Variations
4.3 Variation Instruction
4.4 Issuance of Variations After Practical Completion
4.5 Issuance of AI on P.C. Sums and Provisional Sums
4.6 Valuation of Variation
4.7 Rules of Valuation for Variation
4.8 Additional Expense Caused by Variation
5 Practical Completion and Defects Liability
5.1 Comparison of Practical Completion and Defects Liability Clause Between PAM Form 2018 and the Selected Standard Form of Contracts
5.2 The Requirements to Achieve Practical Completion
5.3 The Definition of Practical Completion
5.4 Practical Completion
5.5 The Notification
5.6 Procedures Subsequent to the Notice of Practical Completion
5.7 Procedures Subsequent to Rejection of Practical Completion
5.8 Consequences of Default to Issue or Reject Within the Stipulated Timeline
5.9 Obligation to Return Possession of the Site
5.10 Failure to Attend to the Works and Defects of a Minor Nature
5.11 Definition of Defects
5.12 Rectification of Defects
5.13 Failure to Attend to the Defects
5.14 Costs of Remedying Defects
5.15 Dispute on Who Has Caused the Defects
5.16 Making Good Defects
6 Damages for Non-Completion
6.1 Comparison of Damages for Non-Completion Clause Between PAM Form 2018 and the Selected Standard Form of Contracts
7 Extension of Time
7.1 Commentary on Extension of Time
7.2 Contents and Adequacy of the Application for Extension of Time
7.3 Other Considerations
7.4 After the Certificate of Non-Completion
8 Loss and/or Expense
8.1 Comparison of Loss and/or Expense Provisions in PAM Form 2018 and the Selected Standard Form of Contracts
8.2 Risk Allocations on Loss and/or Expense
8.3 Grounds to Claim for Loss and/or Expense Not Provided in PAM Form 2018
8.4 Procedure in the Last Stages of the Claims Process
8.5 The Ascertained Amount
9 Payment Application and Issuance of Architect’s Certificate
9.1 Comparison of Payment Application and Issuance of Architect’s, Contract Administrator’s and Certifier’s Certificates Between PAM Form 2018 and the Selected Standard Form of Contracts
10 Arbitration
10.1 Comparison of Arbitration Clause Between PAM Form 2018 and the Other Standard Form of Contracts
11 Performance Bond
11.1 Comparison of Performance Bond Provisions in PAM Form 2018 and the Selected Standard Form of Contracts
Division 3: Detailed Commentary of the PAM Form 2018 and Comparison Between PAM Form 2018 and the Selected Standard Form of Contracts
i Overview
1 Clause 1.0: Contractor’s Obligations
1.0 Overview
1.1 Clause 1.1: Completion of Works in Accordance with Contract Documents
1.2 Clause 1.2: Temporary Work and Construction Method
1.3 Clause 1.3: Contractor’s Design and Responsibilities
1.4 Clause 1.4: Discrepancy or Divergence Between Documents
2 Clause 2.0: Architect’s Instructions (“AI”)
2.0 Overview
2.1 Clause 2.1: Contractor to Comply with AI
2.2 Clause 2.2: Architect’s Instructions
2.3 Clause 2.3: Provisions Empowering Instructions
2.4 Clause 2.4: Failure of Contractor to Comply with AI
3 Clause 3.0: Contract Documents, Programme and As-built Drawings
3.1 Clause 3.1: Contract Documents
3.2 Clause 3.2: Custody of Tender Documents
3.3 Clause 3.3: Copies of Documents
3.4 Clause 3.4: Further Drawings or Details
3.5 Clause 3.5: Works Programme
3.6 Clause 3.6: Programme Not Part of Contract
3.7 Clause 3.7: Architect’s Acceptance of Programme
3.8 Clause 3.8: Availability of Documents
3.9 Clause 3.9: Limitation of Use of Documents
3.10 Clause 3.10: As-built Drawings and Operation and Maintenance Manuals
4 Clause 4.0: Statutory Obligations, Notices, Fees and Charges
4.1 Clause 4.1: Statutory Requirements
4.2 Clause 4.2: Inconsistencies with Statutory Requirements
4.3 Clause 4.3: Conforming to Statutory Obligations
4.4 Clause 4.4: Fees, Levies and Charges
5 Clause 5.0: Levels and Setting Out of the Works
5.0 Overview
5.1 Clause 5.1: Setting Out
6 Clause 6.0: Materials, Goods and Workmanship to Conform to Description, Testing and Inspection
6.0 Overview
6.1 Clause 6.1: Standard of Works, Materials, Goods and Workmanship
6.2 Clause 6.2: Provision of Vouchers
6.3 Clause 6.3: Inspection and Testing
6.4 Clause 6.4: Contractor’s Obligation Not Relieved
6.5 Clause 6.5: Works Not in Accordance with the Contract
6.6 Clause 6.6: No Compensation for Time and Cost
6.7 Clause 6.7: Failure of Contractor to Comply
6.8 Clause 6.8: Warranties in Respect of Materials and Goods
7 Clause 7.0: Royalties and Intellectual Property Rights
7.0 Overview
7.1 Clause 7.1: Indemnity to Owner
7.2 Clause 7.2: Contractor’s Liability to Pay
7.3 Clause 7.3: Government Royalties
8 Clause 8.0: Site Agent
8.0 Overview
8.1 Clause 8.1: Site Agent
8.2 Clause 8.2: Instructions to Site Agent
8.3 Clause 8.3: Exclusion of Person Employed on the Works
9 Clause 9.0: Access to the Works
9.0 Overview
9.1 Clause 9.1: Access to the Works
10 Clause 10.0: Site Staff
10.0 Overview
10.1 Clause 10.1: Duty of Site Staff
10.2 Clause 10.2: Directions Given by Site Staff
11 Clause 11.0: Variations, Provisional and Prime Cost Sums
11.0 Overview
11.1 Clause 11.1: Definition of Variation
11.2 Clause 11.2: No Variations Required by Architect Shall Vitiate Contract
11.3 Clause 11.3: Issue of Variations After Practical Completion
11.4 Clause 11.4: AI on P.C. Sums and Provisional Sums
11.5 Clause 11.5: Valuation of Variations and Provisional Sums
11.6 Clause 11.6: Valuation Rules
11.7 Clause 11.7: Additional Expense Caused by Variation
11.8 Clause 11.8: Access to Contractor’s Books and Documents
11.9 Clause 11.9: Variations and Additional Expenses Added to Contract Sum
12 Clause 12.0: Contract Bills
12.0 Overview
12.1 Clause 12.1: Measurement of Building Works
12.2 Clause 12.2: Correction of Errors or Omissions
Chapters Contents
Clauses in PAM Form 2018
13.0 Clause 13.0: Contract Sum
13.0 Overview
13.1 Clause 13.1: Contract Sum not to be adjusted or altered
14.0 Clause 14.0: Materials and Goods
14.0 Overview
14.1 Clause 14.1: Materials and goods not to be removed
14.2 Clause 14.2: Materials and goods included in certificates
14.3 Clause 14.3: Responsibility for materials and goods
14.4 Clause 14.4: Warranty of title of goods and materials
15.0 Clause 15.0: Practical Completion and Defects Liability
15.0 Overview
15.1 Clause 15.1: Practical Completion
15.2 Clause 15.2: Certificate of Practical Completion
15.3 Clause 15.3: Contractor’s failure to comply with undertaking
15.4 Clause 15.4: Schedule of Defects
15.5 Clause 15.5: Instruction to make good defects
15.6 Clause 15.6: Certificate of Making Good Defects
16.0 Clause 16.0: Partial Possession By Employer
16.0 Overview
16.1 Clause 16.1: Possession of Occupied Part with consent
16.2 Clause 16.2: Possession of Occupied Part without consent
16.3 Clause 16.3: Contractor to remove equipment
17.0 Clause 17.0: Assignment and Sub-Contracting
17.0 Overview
17.1 Clause 17.1: Assignment by Employer
17.2 Clause 17.2: Assignment by Contractor
17.3 Clause 17.3: No sub-contracting
18.0 Clause 18.0: Injury to Person or Loss and/or Damage of Property and Indemnity to Employer
18.0 Overview
18.1 Clause 18.1: Contractor’s indemnity against injury or death
18.2 Clause 18.2: Contractor’s indemnity against loss and/or damage
18.3 Clause 18.3: Contractor’s indemnity against claims by workmen
18.4 Clause 18.4: Indemnities not to be defeated
19.0 Clause 19.0: Insurance Against Injury to Person or Loss and/or Damage of Property
19.0 Overview
19.1 Clause 19.1: Contractor to insure against injury to person and loss and/or damage of property
19.2 Clause 19.2: Employees’ social security scheme for local workmen
19.3 Clause 19.3: Insurance for local workmen not subject to SOCSO
19.4 Clause 19.4: Workmen’s compensation insurance for foreign workers
19.5 Clause 19.5: Placing of insurance with licensed insurance companies
20.0 Clauses 20.A, 20.B & 20.C: Insurance of Buildings/Works
20.0 Overview
20.A Clause 20.A: Insurance Of New Buildings/Works – By The Contractor
20.A.1 Clause 20.A.1: Contractor’s risks – new buildings/works
20.A.2 Clause 20.A.2: Additional risks to be covered under the insurance
20.A.3 Clause 20.A.3: Placing of insurance with licensed insurance companies
20.A.4 Clause 20.A.4: Application of insurance claim proceeds
20.B Clause 20.B: Insurance Of New Buildings/Works – By The Employer
20.B.1 Clause 20.B.1: Insurance by Employer
20.B.2 Clause 20.B.2: Additional risks required by the Contractor
20.B.3 Clause 20.B.3: Maintenance of policy
20.B.4 Clause 20.B.4: Failure of Employer to insure
20.B.5 Clause 20.B.5: Application of insurance claim proceeds
20.C Clause 20.C: Insurance Of Existing Building or Extension – By The Employer
20.C.1 Clause 20.C.1: Employer’s risks – existing building or extension
20.C.2 Clause 20.C.2: Additional risks required by the Contractor
20.C.3 Clause 20.C.3: Maintenance of insurance by Employer
20.C.4 Clause 20.C.4: Failure of Employer to insure
20.C.5 Clause 20.C.5: Application of insurance claim proceeds
21.0 Clause 21.0: Date of Commencement, Postponement and Completion Date
21.0 Overview
21.1 Clause 21.1: Commencement and Completion
21.2 Clause 21.2: Sectional Commencement Dates
21.3 Clause 21.3: Sectional Completion Dates
21.4 Clause 21.4: Postponement or suspension of the Works
Volume 2
22.0 Clause 22.0: Damages for Non-Completion
22.0 Overview
22.1 Clause 22.1: Liquidated Damages and Certificates of Non-Completion
22.2 Clause 22.2: Agreed Liquidated Damages amount
22.3 Clause 22.3: Certificate of Non-Completion revoked by subsequent Certificate of Extension of Time
23.0 Clause 23.0: Extension of Time
23.0 Overview
23.1 Clause 23.1: Submission of notice and particulars for extension of time
23.2 Clause 23.2: Delay by Nominated Sub-Contractor
23.3 Clause 23.3: Insufficient information
23.4 Clause 23.4: Certificate of Extension of Time
23.5 Clause 23.5: Other consideration for extension of time
23.6 Clause 23.6: Contractor to prevent delay
23.7 Clause 23.7: Notification to Nominated Sub-Contractors
23.8 Clause 23.8: Relevant Events
23.9 Clause 23.9: Extension of time after the issuance of Certificate of Non-Completion
23.10 Clause 23.10: Architect’s review of extension of time after practical completion
24.0 Clause 24.0: Loss and/or Expense Caused by Matters Affecting The Regular Progress Of The Works
24.0 Overview
24.1 Clause 24.1: Loss and/or expense caused by matters affecting the regular progress of the works
24.2 Clause 24.2: Access to Contractor’s books and documents
24.3 Clause 24.3: Matters materially affecting the regular progress of the Works
24.4 Clause 24.4: Loss and/or expense to be included in certificate
25.0 Clause 25.0: Determination of Contractor’s Employment by Employer
25.0 Overview
25.1 Clause 25.1: Defaults by Contractor
25.2 Clause 25.2: Procedure for determination
25.3 Clause 25.3: Contractor’s insolvency
25.4 Clause 25.4: Rights and duties of employer and contractor
25.5 Clause 25.5: Records of Works
25.6 Clause 25.6: Final Account upon determination
25.7 Clause 25.7: Remedy limited to damages only
25.8 Clause 25.8: Employer’s rights and remedies not prejudiced
26.0 Clause 26.0: Determination of Own Employment by Contractor
26.0 Overview
26.1 Clause 26.1: Defaults by Employer
26.2 Clause 26.2: Procedure for determination
26.3 Clause 26.3: Employer’s insolvency
26.4 Clause 26.4: Rights and duties of Contractor and Employer
26.5 Clause 26.5: Records of Works
26.6 Clause 26.6: Settlement of accounts
26.7 Clause 26.7: Contractor’s rights and remedies not prejudiced
27.0 Clause 27.0: Nominated Sub-Contractors
27.0 Overview
27.1 Clause 27.1: P.C. Sums and Provisional Sums – Nominated Sub-Contractors
27.2 Clause 27.2: Nomination of sub-contractor
27.3 Clause 27.3: Objection to nomination of Sub-Contractor
27.4 Clause 27.4: Action following objection of Nominated Sub-Contractor
27.5 Clause 27.5: Payment by Contractor to Nominated Sub-Contractors
27.6 Clause 27.6: Failure of Contractor to pay Nominated Sub-Contractors
27.7 Clause 27.7: Final payment to Nominated Sub-Contractors
27.8 Clause 27.8: Determination of Nominated Sub-Contractor’s employment
27.9 Clause 27.9: Contractor’s responsibility for Nominated Sub-Contractors
27.10 Clause 27.10: Employer has no privity of contract with Nominated Sub-Contractors
27.11 Clause 27.11: Re-nomination of sub-contractor due to determination by the Contractor
27.12 Clause 27.12: Re-nomination of sub-contractor due to determination by the Nominated Sub-Contractor
27.13 Clause 27.13: Contractor to recover additional expenses from Nominated Sub-Contractor
27.14 Clause 27.14: Contractor permitted to tender for P.C. Sums
28.0 Clause 28.0: Nominated Suppliers
28.0 Overview
28.1 Clause 28.1: P.C. Sums and Provisional Sums – Nominated Suppliers
28.2 Clause 28.2: Nominated Suppliers and their obligations
28.3 Clause 28.3: Objection to Nominated Suppliers
28.4 Clause 28.4: Action following objection of suppliers
28.5 Clause 28.5: Value of materials and goods supplied by Nominated Suppliers
28.6 Clause 28.6: Payment to Nominated Suppliers
28.7 Clause 28.7: Contractor’s liability for Nominated Suppliers
28.8 Clause 28.8: Employer no privity of Contract with Nominated Suppliers
29.0 Clause 29.0: Works By Craftsmen, Tradesmen Or Other Contractors Employed Or Engaged By Employer
29.0 Overview
29.1 Clause 29.1: Works by Employer’s Craftsmen
30.0 Clause 30.0: Certificates and Payments
30.0 Overview
30.1 Clause 30.1: Payment application and issuance of Architect’s certificate
30.2 Clause 30.2: Amount due in Architect’s certificate
30.3 Clause 30.3: Errors in payment certificate
30.4 Clause 30.4: Set-off by Employer
30.5 Clause 30.5: Retention fund
30.6 Clause 30.6: Rules regarding Retention Fund
30.7 Clause 30.7: Suspension of Works for non-payment
30.8 Clause 30.8: Compulsory suspension of Works
30.9 Clause 30.9: Cessation insurance resulting from suspension of the Works
30.10 Clause 30.10: Final Account
30.11 Clause 30.11: Items in Final Account
30.12 Clause 30.12: Conclusiveness of the Final Account
30.13 Clause 30.13: Issuance of Penultimate Certificate
30.14 Clause 30.14: Issue of Final Certificate
30.15 Clause 30.15: Final Certificate
30.16 Clause 30.16: Final Certificate not conclusive
30.17 Clause 30.17: Interest
31.0 Clause 31.0: Outbreak of Hostilities
31.0 Overview
31.1 Clause 31.1: Hostilities – Determination by Employer or Contractor
31.2 Clause 31.2: Notices of determination
31.3 Clause 31.3: AI regarding protective work
31.4 Clause 31.4: Payment resulting from determination
32.0 Clause 32.0: War Damage
32.0 Overview
32.1 Clause 32.1: Procedures Following War Damage
32.2 Clause 32.2: Definition of War Damage
33.0 Clause 33.0: Antiquities
33.0 Overview
33.1 Clause 33.1: Antiquities property of Employer
34.0 Clause 34.0: Mediation
34.0 Overview
34.1 Clause 34.1: Mediation under PAM Rules
34.2 Clause 34.2: Mediation does not prejudice the parties’ rights to arbitration
35.0 Clause 35.0: Expert Determination
35.0 Overview
35.1 Clause 35.1: Disputes on all matters
35.2 Clause 35.2: Expert determination under PAM Rules
35.3 Clause 35.3: Expert determination shall not prejudice the parties’ rights to adjudication or arbitration
36.0 Clause 36.0: Adjudication
36.0 Overview
36.1 Clause 36.1: Set-off disputes referred to adjudication
36.2 Clause 36.2: Notice to refer to adjudication
36.3 Clause 36.3: Adjudication Rules
36.4 Clause 36.4: Decision of the adjudicator
37.0 Clause 37.0: Arbitration
37.0 Overview
37.1 Clause 37.1: Disputes referred to arbitration
37.2 Clause 37.2: Procedures for appointment of arbitrator
37.3 Clause 37.3: Arbitration Act and Rules
37.4 Clause 37.4: Powers of arbitrator
37.5 Clause 37.5: Consolidation of arbitration proceedings
37.6 Clause 37.6: Commencement of arbitration proceeding
37.7 Clause 37.7: Arbitrator’s award to be final and binding on parties
38.0 Clause 38.0: Notice
38.0 Overview
38.1 Clause 38.1: Notice
38.2 Clause 38.2: Notice deem served
38.3 Clause 38.3: Proof of Notice
38.4 Clause 38.4: Written communication
39.0 Clause 39.0: Performance Bond
39.0 Overview
39.1 Clause 39.1: Submission of Performance Bond
39.2 Clause 39.2: Form of the Performance Bond
39.3 Clause 39.3: Validity of the Performance Bond
39.4 Clause 39.4: Failure to extend the validity
39.5 Clause 39.5: Payments from the Performance Bond
39.6 Clause 39.6: Return of Performance Bond
40.0 Clause 40.0: Governing Law
40.1 Clause 40.1: Governing Law
Division 4 – Other Clauses in Selected Standard Form of Building Contracts Not Found in PAM Form 2018
1 Overview
2 Contractor’s General Obligations
2.1 AIAC (2019)
2.2 PWD 203A
2.3 CIDB (2000)
2.4 IEM (2017)
2.5 FIDIC Red Book (2017)
3 Materials, Goods and Workmanship
3.1 PWD 203A
3.2 CIDB (2000)
3.3 JCT (2016)
4 Variation, Provisional and Prime Cost Sums
4.1 FIDIC Red Book (2017)
4.2 JCT (2016)
5 Practical Completion and Defects Liability
5.1 PWD 203A
5.2 CIDB (2000)
5.3 FIDIC Red Book (2017)
6 Damages for Non-Completion
6.1 CIDB (2000)
6.2 FIDIC Red Book (2017)
7 Extension of Time
7.1 AIAC (2019)
8 Loss and/or Expense
8.1 AIAC (2019)
9 Payment Application and Issuance of Architect’s Certificate
9.1 AIAC (2019)
9.2 FIDIC Red Book (2017)
9.3 JCT (2016)
10 Arbitration
10.1 AIAC (2019)
10.2 CIDB (2000)
10.3 FIDIC Red Book (2017)
11 Performance Bond
11.1 AIAC (2019)
11.2 PWD 203A
12 Inspection of Site
12.1 PWD 203A
12.2 FIDIC Red Book (2017)
13 Bills of Quantities and Provisional Quantities
13.1 PWD 203A
14 Soil Investigation
14.1 IEM (2017)
15 Planning Approval
15.1 IEM (2017)
16 Labour
16.1 PWD 203A
16.2 CIDB (2000)
16.3 IEM (2017)
16.4 FIDIC Red Book (2017)
17 Public Interference
17.1 AIAC (2019)
17.2 IEM (2017)
17.3 FIDIC Red Book (2017)
18 Transport and Public Roads
18.1 IEM (2017)
19 Use of Explosives
19.1 IEM (2017)
20 Facilities for Other Contractors
20.1 AIAC (2019)
20.2 PWD 203A
20.3 IEM (2017)
20.4 FIDIC Red Book (2017)
21 Materials and Equipment Supplied by the Employer
21.1 IEM (2017)
22 Ownership of Excavated Materials
22.1 IEM (2017)
23 Constructional Plant and Equipment
23.1 PWD 203A
23.2 IEM (2017)
24 Slow Progress of Construction/Expediting Progress of Works
24.1 CIDB (2000)
24.2 IEM (2017)
24.3 FIDIC Red Book (2017)
25 Early Use by the Employer
25.1 JCT (2016)
26 Information Release Schedule
26.1 JCT (2016)
27 Selection of Domestic Sub-Contractors
27.1 JCT (2016)
28 Insurance/Indemnity
28.1 JCT (2016)
28.2 FIDIC Red Book (2017)
29 Assignment, Third Party Rights and Collateral Warranties
29.1 JCT (2016)
30 Termination/Determination
30.1 AIAC (2019)
30.2 PWD 203A
30.3 CIDB (2000)
30.4 JCT (2016)
30.5 FIDIC Red Book (2017)
31 Release from Performance under the Law
31.1 FIDIC Red Book (2017)
32 General
32.1 PWD 203A
32.2 AIAC (2019)
32.3 CIDB (2000)
32.4 FIDIC Red Book (2017)
33 Employer
33.1 FIDIC Red Book (2017)
34 Architect/Contract Administrator/Engineer
34.1 AIAC (2019)
34.2 CIDB (2000)
34.3 IEM (2017)
34.4 FIDIC Red Book (2017)
35 Advance Warning by Both Parties
35.1 FIDIC Red Book (2017)
36 Test on Completion
36.1 CIDB (2000)
36.2 FIDIC Red Book (2017)
37 Measurement and Valuation
37.1 PWD 203A
37.2 CIDB (2000)
37.3 FIDIC Red Book (2017)
38 Care of the Works
38.1 FIDIC Red Book (2017)
39 Fluctuation of Price
39.1 PWD 203A
39.2 JCT (2016)
40 Time is of Essence
40.1 PWD 203A
– Conclusion
– Index
Category:
Weight 3.7 kg

Customer Reviews

There are no reviews yet.

Only logged in customers who have purchased this product may leave a review.